Besix完成了巴林液化天然气的工作

    中国石化新闻网讯 据世界天然气9月17日报道,比利时工程公司Besix周日表示,已完成位于穆哈拉格岛
    近海的巴林液化天然气(LNG)进口码头的设计和建造。     根据Besix声明,工作范围包括在钻孔和灌浆桩桩上建造的LNG码头的设计和建造,最大长度为55米,海上
    约5公里,海底水平为-18米。     该项目还包括一个600米长的瓦砾堆海上防波堤和混凝土装甲单元。     “该项目的许多方面都非常具有挑战性,例如完成公海的海上工程,包括完成超优化设计所需的专业设备
    和海上团队,” 巴林Besix经理Yasser Laroussi说。     “不幸的是,由于天气恶劣,我们也有过度延误。这一点,再加上充满挑战的物流和紧张的时间表,给团
    队带来了额外的压力,但我们成功地应对了这些挑战,并按时完成了所有合同里程碑,“Laroussi补充道
    。     码头的建设于2016年11月开始,第一批永久桩于2017年5月底完工。     所有永久性工程仅在14个月内完成,总计300万工时,零损失时间事件,Besix称补充说项目移交已于9月4
    日完成。     李方征 编译自 世界天然气     原文如下:     Besix completes Bahrain LNG work     Belgian engineering company Besix said on Sunday it had completed the design and
    construction of the Bahrain liquefied natural gas (LNG) import terminal, located offshore
    Muharraq Island.     The scope of work included the design and construction of an LNG jetty constructed on
    drilled and grouted pin piles with a maximum length of 55 metres, located approximately 5km
    offshore and with a seabed level at -18 metres, according to a Besix statement.     The project also included a 600-metre long rubble mound offshore breakwater with concrete
    armour units.     “Many aspects of the project have been quite challenging, such as completing the offshore
    works in the open sea, including the specialised equipment and offshore teams required to
    complete the ultra-optimised design,” said Yasser Laroussi, Besix manager in Bahrain.     “Unfortunately, we also had excessive delays due to bad weather. This, coupled with
    challenging logistics and the tight schedule, added additional pressure to the team, but we
    tackled those challenges successfully and completed all the contractual milestones on time,
    ” added Laroussi.     Construction on the terminal commenced in November 2016, with the first permanent pile
    completed by the end of May 2017.     All permanent works were completed in only 14 months, with a total of 3 million man-hours
    with zero lost time incidents, Besix said adding that the project handover was completed on
    September 4.