诺瓦泰克亚马尔液化天然气项目已完成89%

中国石化新闻网讯 据路透社10月26日莫斯科报道,俄罗斯最大的独立天然气生产公司诺瓦泰克(Novatek)周四在莫斯科宣布,该公司的整个亚马尔液化天然气(LNG)项目迄今已完成89%,其中包括第一条LNG生产线已完成97%。 诺瓦泰克早些时候曾说,考虑到第四条LNG生产线,整个亚马尔LNG项目的LNG总年产能将达到1750万吨。 诺瓦泰克总裁列昂尼德·米赫尔松上周曾说,亚马尔LNG项目的第一条LNG生产线将在今年年底前启动,而其它LNG生产线将提前进行试运转。 第二条LNG生产线预计将在明年第三季度启动,而第三条LNG生产线将在2019年投产。 李峻 编译自 路透社 原文如下: Russia’s Novatek says entire Yamal LNG project is 89% complete Independent Russian gas producer Novatek said on Thursday its entire Yamal LNG project was 89% complete, including the first train which is 97% complete. Total Yamal LNG capacity is seen at 17.5 MMt of LNG per year, taking into account the fourth train, the company had said earlier. Novatek head Leonid Mikhelson said last week that the first train of Yamal LNG would be launched by the year-end, while other trains would be commissioned ahead of schedule. The second train is expected to be launched in the Q3 2018, while the third train will start working in 2019.
 