中国石化新闻网讯 据普氏能源资讯休斯敦8月22日消息,南非沙索公司在二季度业绩报告中表示,公司位于路易斯安娜州西湖的莱克查尔斯化工项目(LCCP)将在明年下半年开始逐步投产,当前整个项目的工程进度完成74%,建设进度完成42%。 沙索公司已经表示,在第一阶段的开工中,线性低密度聚乙烯(LLDPE)装置将成为首套投产的装置,预计在明年下半年投产,随后154万吨/年的乙烷裂解装置和环氧乙烷/乙二醇装置将在明年晚些时候投产。 第二阶段开工的装置包括一套低密度聚乙烯(LDPE)装置钭在2019年初投产,另外三套生产特种乙醇、乙氧基化合物和氧化铝产品的小型衍生物装置将在2019年下半年陆续投产。 尤胜皓 摘译自 普氏能源资讯 原文如下: Sasol Louisiana chemicals complex on track for H2 2018 startup Sasol’s Lake Charles Chemicals Project (LCCP) in Westlake, Louisiana, is on track for a phased startup beginning in second half of 2018, with overall completion at 74% and construction at 42%, the company said in a presention of its second quarter earnings. In the first wave of startups, the first unit — a linear low-density polyethylene unit — is expected to start up in the H2 2018, followed by a 1.54 million mt/year ethane-fed steam cracker and an ethylene oxide/ethylene glycol unit later that year, the company has said. The second wave includes startup of a low-density PE unit in early H1 2019, and startup of three smaller derivative plants that will produce specialty alcohols, ethoxylates and alumina products in H2 2019.
未经允许,不得转载本站任何文章: