中国石化新闻网讯 据路透社10月9日墨尔本报道,位于珀斯的伍德塞德能源公司已经选择贝克特尔作为优先执行承包商,计划扩建位于澳大利亚西部卡拉沙(Karratha)附近伯鲁普半岛(Burrup Peninsula)的Pluto液化天然气设施。 伍德塞德表示其将于贝克特尔就准备授予Pluto项目的前端工程和设计阶段的合同而密切合作。 该提议是对Pluto液化天然气设施进行棕地扩建,包括建造第二条液化天然气生产线,目标产能为每年400 – 500万吨,以及开发近海斯卡伯勒气田7.3万亿立方英尺的天然气资源。 伍德塞德目标在2019年第三季度开展前度设计与工程,最终投资决策时间安排在2020年。 按照时间表,第二条生产线目标在2024年全面投产。 蔡小全 编译自 路透社 原文如下: Woodside choses contractor for Pluto LNG Train 2 Woodside Energy Ltd., Perth, has chosen Bechtel as the preferred execution contractor for the proposed expansion of its Pluto LNG facility on the Burrup Peninsula near Karratha in Western Australia. Woodside said it would work closely with Bechtel in preparation for award of the contract for the front-end engineering and design phase of the Pluto project. The proposal is for a brownfield expansion of the Pluto LNG facility, including construction of a second LNG train with a targeted capacity of 4-5 million tonnes/year and the development of the 7.3 tcf of offshore Scarborough field’s gas resource. Woodside is aiming to begin FEED during third-quarter 2019 with a final investment decision scheduled for 2020. On that timetable, Train 2 is targeted to be brought on stream in 2024.
未经允许,不得转载本站任何文章: